NEC ECC: Insurances Post Completion
|
|
4
|
554
|
15 November 2018
|
NEC ECC: Defect or covered by Insurance
|
|
1
|
474
|
8 November 2018
|
NEC3: Design liability on Contractor proposed equipment/built elements
|
|
1
|
325
|
10 October 2018
|
NEC ECC: Stolen Equipment
|
|
1
|
798
|
15 November 2017
|
NEC ECC: Risk Allocation
|
|
1
|
1391
|
11 April 2017
|
NEC ECC: Risk allocation - how is it allocated or capped?
|
|
2
|
1876
|
6 April 2017
|
NEC3 ECC: Is the Contractor required to procure Professional Indemnity Insurance because he has design responsibility for temporary works?
|
|
1
|
2693
|
22 June 2016
|
NEC3 ECC: Clause 80.1 - Employer's Risks: Claims etc as unavoidable result of the works
|
|
1
|
1696
|
7 June 2016
|
NEC3 ECC: 80.1 - Claims, proceedings, compensation and costs payable due to a fault of the Employer, does this just refer to insurance claims or can it refer to any event?
|
|
1
|
1664
|
30 August 2015
|
NEC3 ECC Option C: should the Client be paying for the Contractor's Site Insurance Cost?
|
|
1
|
507
|
26 August 2015
|
NEC3 ECC: Management of Utilities and associated risk?
|
|
2
|
705
|
12 May 2015
|
NEC3 ECC: Insurance excess
|
|
2
|
1042
|
8 April 2015
|
NEC3 ECC: Insurance excess related to a compensation event
|
|
1
|
1100
|
7 April 2015
|
NEC3 ECC: Compensation events and associated insurance
|
|
1
|
490
|
31 March 2015
|
What remedies are available to the Project Manager if a Contractor refuses to extend his performance bond and what clause applies when the Contractor is to comply with a programme compiled by the PM?
|
|
2
|
879
|
19 November 2014
|
Which Party owns terminal float?
|
|
1
|
759
|
15 November 2012
|
What happens if TRA (Time Risk Allowance) is not needed by the Contractor?
|
|
1
|
766
|
15 November 2012
|
What is Time Risk Allowance (TRA)?
|
|
1
|
1321
|
15 November 2012
|
The Contractor has insured a risk which the Employer was contractually obliged to insure but did not. Who pays the cost of this insurance?
|
|
1
|
567
|
11 October 2012
|
What should the Contractor do if the Employer does not insure a risk which the contract requires the Employer to insure?
|
|
1
|
519
|
11 October 2012
|
Does the Contractor’s acceptance of an insurance policy or certificate provided by the Employer change the responsibility of the Employer to provide the insurances stated in the Contract Data?
|
|
1
|
505
|
11 October 2012
|
What should the Contractor do if there is a discrepancy between the Employer-provided insurances as stated in the Contract Data and the Employer-provided insurances as actually given?
|
|
1
|
514
|
11 October 2012
|
If the Employer enters high levels of deductibles in the Contract Data, why might tenderers insure all or part of the deductible amount?
|
|
1
|
494
|
11 October 2012
|
What would be the implications of entering high levels of deductibles in the Contract Data?
|
|
1
|
517
|
11 October 2012
|
What would be the implications of entering very low amounts against the deductibles in the Contract Data?
|
|
1
|
478
|
11 October 2012
|
What should the Employer do if he is unsure about what level of deductibles (excesses) to apply insurance policies?
|
|
1
|
458
|
11 October 2012
|
Why might the Contractor not accept the terms of the insurance policies which the Employer has provided?
|
|
1
|
435
|
11 October 2012
|
When does the Project Manager submit policies and certificates for insurances provided by the Employer to the Contractor?
|
|
1
|
463
|
11 October 2012
|
If the Employer decides to insure a risk which the Contractor was required to insure but did not, who pays the cost of the insurance?
|
|
1
|
472
|
11 October 2012
|
What if the Employer decides not to insure a risk which the Contractor should have insured but did not?
|
|
1
|
462
|
11 October 2012
|