BI Toolkit
BI Toolkit
ReachBack
If the contractor or sub-contractor need borrow money at excessively high rates, can this be recovered?
Legal and Disputes
Contractor Claims
Legal_Expert
18 January 2013 11:12
2
Yes, where it can be shown that this was caused by the employer.
Related topics
Topic
Replies
Views
Activity
When are finance charges likely to be accepted?
Contractor Claims
1
506
18 January 2013
When an architect is charged extra fess for work which results from a contractor breaching certain obligations, can the employer recover these fees from the contractor?
JCT Contracts
1
443
5 February 2013
Why is it important to provide a well presented and evidenced claim?
Contractor Claims
1
573
18 January 2013
What impact does the alleged poor performance of a contractor have on the acceleration process?
Contractor Claims
1
455
18 January 2013
When are employers as parties to a contract entitled to damages?
Contractor Claims
1
508
18 January 2013