ReachBack
If the contractor or sub-contractor need borrow money at excessively high rates, can this be recovered?
Legal and Disputes
Contractor Claims
Legal_Expert
18 January 2013 11:12
2
Yes, where it can be shown that this was caused by the employer.
Related Topics
Topic
Replies
Views
Activity
NEC ECC: Can the Employer recover its costs where a Contractor is self-accelerating by working weekends?
General
2
409
17 June 2020
NEC ECC: Option A - Can the Employer recover 3rd Party costs incurred due to Contractor error?
General
1
625
10 January 2019
When an architect is charged extra fess for work which results from a contractor breaching certain obligations, can the employer recover these fees from the contractor?
JCT Contracts
1
407
5 February 2013
Are there any issues related to interest charges for which contractors need to have awareness?
Contractor Claims
1
445
18 January 2013
Is it right to assume that a contractor would have a claim for breach by the employer (under 60.1.18) for the consequences (delay / disruption if proven) for late payment by the employer (other than an interest claim)
Payment
1
849
30 September 2014