|
Is there any element to pay particular heed to with regard to variations?
|
|
1
|
424
|
18 January 2013
|
|
What are the key points to pay heed to with regard to claims?
|
|
1
|
503
|
18 January 2013
|
|
What is the primary reason that claims are rejected?
|
|
1
|
475
|
18 January 2013
|
|
Why is it important to provide a well presented and evidenced claim?
|
|
1
|
576
|
18 January 2013
|
|
To whom should a financial claim for loss and expense be submitted to?
|
|
1
|
535
|
18 January 2013
|
|
Why might a contract stipulate a duration for a job rather than a commencement and completion date?
|
|
1
|
517
|
18 January 2013
|
|
During a contract, can an architect or engineer extend the completion date?
|
|
1
|
468
|
18 January 2013
|
|
What is the procedure when a contract does not stipulate a completion date?
|
|
1
|
638
|
18 January 2013
|
|
What are the consequences if a contract misses its completion date?
|
|
1
|
423
|
18 January 2013
|
|
What element forms the basis of many disputes in construction and engineering contracts?
|
|
1
|
464
|
18 January 2013
|
|
Is there an alternative way of calculating profit, aside from subtracting costs to date from the sum stipulated in the contract?
|
|
1
|
482
|
18 January 2013
|
|
When a contractor makes a claim for loss of profit what should the calculation be based on
|
|
1
|
448
|
18 January 2013
|
|
What are the consequences of an an employer deciding to take work from one contractor on site and give it to another?
|
|
1
|
446
|
18 January 2013
|
|
Under what circumstances could a contractor argue his / her entitlement to loss of profit?
|
|
1
|
466
|
18 January 2013
|
|
With regards to loss and expense, what is the guiding principle that should be applied to contract provisions?
|
|
1
|
468
|
18 January 2013
|
|
Which case covers a contractor seeking his indirect costs?
|
|
1
|
425
|
18 January 2013
|
|
How can 'direct costs' be defined?
|
|
1
|
523
|
18 January 2013
|
|
How can 'damages' be defined for the purpose of a contract?
|
|
1
|
452
|
18 January 2013
|
|
When does loss of profit as a head of claim under the IFC form of contract constitute a valid claim?
|
|
1
|
482
|
18 January 2013
|
|
If a claim is not founded on a relevant matter then what is the likely outcome?
|
|
1
|
416
|
18 January 2013
|
|
Does a contractor will have a right to charge additional payment for additional work instructed?
|
|
1
|
500
|
18 January 2013
|
|
Is it permissible to submit new evidence in addition to the original reply?
|
|
1
|
620
|
18 January 2013
|
|
Does the adjudicator ever have to consider relevant arguments and evidence submitted outside of the stated timescales?
|
|
1
|
635
|
18 January 2013
|
|
What influence does the the Housing Grants, Construction and Regeneration Act, 1996 have on the process?
|
|
1
|
524
|
18 January 2013
|
|
What is the procedure for making a claim for money?
|
|
1
|
642
|
18 January 2013
|
|
Are costs within an adjudicator's jurisdiction?
|
|
1
|
676
|
18 January 2013
|
|
Should costs be claimed as part of a referral?
|
|
1
|
640
|
18 January 2013
|
|
What should a referral for adjudication contain?
|
|
1
|
621
|
18 January 2013
|
|
Who has jurisdiction over any counter-claims that are launched?
|
|
1
|
516
|
18 January 2013
|
|
What is a notice of intention to adjudicate?
|
|
1
|
679
|
18 January 2013
|