What is the procedure when a contract does not stipulate a completion date?

Under these circumstances it is possible for employers to give notice making time of the essence and requiring a contractor to complete by a stipulated date, as in Rickards (Charles) v Oppenheim [1950]1 KB 616). Where the contractor fails to perform by that date the employer would be in a position to reject any further work on the contract.