The adjudicator may be bound to consider relevant arguments and evidence submitted outside of the stated timescales, as to refuse to do so could put him or her in breach of the principles of natural justice. See Balfour Beatty Construction Northern Ltd v Modus Corovest (Blackpool) Ltd [2008] EWHC 3029 (TCC).