What happens if a Defect is not corrected within the Defect Correction Period?

What happens if a Defect is not corrected within the Defect Correction Period?

1 Like

The Employer is allowed to have the Defect corrected by other people and recover the incurred cost from the Contractor (see Clause 45.1). The amount is assessed by the Project Manager.