Does the Project Manager have to notify why he has not accepted the Contractor's programme?

Is the Project Manager obliged to notify why he has not accepted the Contractor’s programme.

The Project Manager is obliged to give reasons why they are not accepting the programme. However, just listing the reason within clause 31.3 is not enough - the Contractor should be left with no question mark as to what they need to do in order to put it right so that it will be accepted. The Accepted Programme should be considered equally important to both Parties.