Why might Key Dates by used rather than Sectional Completion?
On a multi-contract project, the Project Manager or Employer will often require the Contractor’s work to have achieved a defined Condition by a certain date, without necessarily being complete. In that case it will be better to define that Condition by using a Key Date.