Where might Key Dates rather than sectional Completion be used?

Where might Key Dates rather than sectional Completion be used?

Examples of where Key Dates, rather than sectional Completion, should be used include the following:

	The Contractor’s design having reached a defined stage to enable information to be passed to Others so that their design can proceed

	A wall having been built to a certain level so that Others can start to fix their plant to it.

	Completion of some, but not all, of the works on a floor of a multi-storey building so that Others can commence their work, which is to be carried out at the same time as the remainder of the Contractor’s work on that floor.