Where the Contractor is required to design a part of the works, what should the Employer state in the Works Information?

Where the Contractor is required to design a part of the works, what should the Employer state in the Works Information?

1 Like

The criteria to which the Employer wishes the design to conform should be stated in the Works Information. This could include: details of the form, geometry and dimensions of the works; specifications; reference to Site Information; and environmental considerations.