Who provides the Works?
1 Like
The Contractor provides the Works in accordance with the Works Information (see Clause 20.1). This is the Contractor’s basic obligation. ‘Provide the Works’ is defined in Clause 11.2(13). The Works Information is defined in Clause 11.2(19). The Works Information provided by the Employer should state everything the Contractor is to do, including design work.