Where do I put preliminaries in my bid under ECC Option C?
What are termed preliminaries in the traditional contracts are included within the build up for each activity on the Activity Schedule. Managing Reality Book 4 give an example of a traditonal build up for preliminaries and shows how these fit in with the Schedule of Cost Components