When undertaking an JCT Standard Building Contract 2009 contract, an architect approves a contractor's programme, with the completion date indicated post-dating the contract completion date by two months. Should the architect work towards the new date?

There have been several court cases and legal precedents regarding this matter, and the subject can be easily summed up by the following: the programme can never alter the correct date for completion once it is set.