When operating under JCT Standard Building Contract 2009, should an architect not be furnished with the necessary delay information until a week before the due completion date, is there any leeway regarding a time extension being issued before the complet

Under these circumstances, the architect would be required to ‘endeavour’ to provide the information as soon as possible, even though producing it in a week may be unlikely.