What should the Project Manager do when notified by the Contractor that he considers that the Works Information require him to do something which is illegal or impossible?

What should the Project Manager do when notified by the Contractor that he considers that the Works Information require him to do something which is illegal or impossible?

1 Like

If the Project Manager concurs with the Contractor’s view, he gives an instruction to alter the Works Information to remedy the illegality or impossibility (see Clause 18.1). Such a change to the Works Information is a compensation event under Clause 60.1.