Can the Project Manager change the Works Information?

Can the Project Manager change the Works Information?

1 Like

Yes. As stated in Clause 14.3, the Project Manager may issue an instruction to the Contractor which changes the Works Information but all changes of this nature are potentially compensation events under Clause 60.1(1).