What should the Contractor do if he changes a method of working so activities on the Activity Schedule do not relate to the operations on the Accepted Programme?

What should the Contractor do if he changes a planned method of working at his discretion so that the activities on the Activity Schedule do not relate to the operations on the Accepted Programme?

If the Contractor changes a planned method of working at his discretion so that the activities on the Activity Schedule do not relate to the operations on the Accepted Programme, he submits a revision of the Activity Schedule to the Project Manager for acceptance (see Clause 54.2).