What is the purpose of Option Y(UK)2?

What is the purpose of Option Y(UK)2?

If the contract is subject to the Housing Grants, Construction and Regeneration Act 1996, Option Y(UK) 2 is incorporated by reference in the Contract Data. Its purpose is to add to the core clause payment provisions in section 5: Payment to ensure that they comply with the Act.