What are the secondary Options?
1 Like
The secondary Options are:
Option X1: Price adjustment for inflation (used only with Options A,B,C and D)
Option X2: Changes in the law
Option X3: Multiple currencies (used only with Options A and B)
Option X4: Parent company guarantee
Option X5: Sectional Completion
Option X6: Bonus for early Completion
Option X7: Delay damages
Option X12: Partnering
Option X13: Performance bond
Option X14: Advanced payment to the Contractor
Option X15: Limitation of the Contractor’s liability for his design to reasonable skill and care
Option X16: Retention (not used with Option F)
Option X17: Low performance damages
Option X18: Limitation of liability
Option X20: Key Performance Indicators (not used with Option X12)
Option Y(UK)2: The Housing Grants, Construction and Regeneration Act 1996
Option Y(UK)3: The Contract (Rights of Third Parties) Act 1999
Option Z: Additional conditions of contract