What do variations to the works consist of?
1 Like
Variations to the works are made by a Project Manager’s instruction to change the Works Information (the authority given to the Project Manager for this is contained in Clause 14.3). A variation may comprise deletion or addition of work or alteration to work. It may include changes to the Employer’s design, to design criteria or to performance requirements for the Contractor’s design.