If, for example, it can be seen that without acceleration the completion of a project would be jeopardised and the resultant loss would be far in excess of the cost of acceleration of an element of work, then it would be remain a valid course of action to accelerate the work and make a related acceleration claim subject to the grounds of that claim being well founded on a recoverable event under the contract.