The Project Manager has decided that the work does not meet the Condition stated for a Key Date and the Employer has incurred costs. Who pays for this cost?

The Project Manager has decided that the work does not meet the Condition stated for a Key Date and the Employer has incurred costs in carrying out work. Who pays for this additional cost?

1 Like

As stated in Clause 25.3, this cost is payed by the Contractor.