What is the procedure if the Project Manager has decided that the work does not meet the Condition stated for a Key Date?

What is the procedure if the Project Manager has decided that the work does not meet the Condition stated for a Key Date?

1 Like

No longer than four weeks after the date when the Condition for the Key Date was missed, the Project Manager will assess the additional cost which the Employer incurs as a consequence.