The Project Manager has decided that the work does not meet the Condition stated for a Key Date and the Employer has incurred costs by paying Others. Who pays for this additional cost?

The Project Manager has decided that the work does not meet the Condition stated for a Key Date and the Employer has incurred costs by paying an additional amount to Others in carrying out work. Who pays for this additional cost?

1 Like

As stated in Clause 25.3, these costs are payed by the Contractor.