NEC3 PSC Key Dates

What remedy does the Employer have where the Consultant fails to meet a Key Date? If delay resulted in costs to the Employer from another project linked to their delay, are these recoverable? Thanks.

See clause 23.3.

Put simply, the Employer is titled to be paid the additional cost they have or will incur on the same project. What the “same project” is may well be a matter for discussion.