The Adjudicator disagrees with the Project Manager’s assessment of delay to the Completion Date. Can he overrule the Project Manager’s decision?
Yes. If the Adjudicator disagrees with the Project Manager’s assessment of delay to the Completion Date, he will overrule the Project Manager’s decision and the Completion Date will be set in accordance with what the Adjudicator decides.