What procedure does the Adjudicator follow if he decides in favour of the Contractor in a dispute but it is too late for the action or inaction to be implemented?
The Adjudicator should deal with the matter by deciding the effect on the Prices and Completion Date using the same assessment procedure that is used for compensation events.