What action may the Adjudicator take?

What action may the Adjudicator take?

The Adjudicator may:

	Review and revise any action or inaction of the Project Manager or Supervisor related to the dispute and alter a quotation which has been treated as having been accepted.

	Take the initiative in ascertaining the facts and the law related to the dispute

	Instruct a Party to provide further information related to the dispute within a stated time and

	Instruct a Party to take any other action which he considers necessary to reach his decision and to do so within a stated time (see Clause W1.3(5)).