If the contractor has hired a subcontractor to execute a Compensation events in its entirety. Since the contractor wont be doing any work, is he entitled to direct fee?
No, he is not. Only subcontract fee percentage on Subcontractor Defined Costs as calculated in accordance with the main contract (assuming an NEC3 ECC option B contract)