When pricing a quotation, is it acceptable for the Main Contractor to apply the direct fee percentage and the subcontracted fee percentage?
1 Like
The answer is âNoâ.
You can have fee on fee in the sense that you the main contract âsubcontracted fee percentageâ is applied to the relevant fee percentage under the subcontract. However, you do not have main contract âdirect fee percentageâ on main contract âsubcontracted fee percentageâ.