Should the interfaces between contractors on Site by mentioned in the Works Information?
1 Like
Yes. It is important that interfaces between contractors are defined in the Works Information. Any services provided by one contractor to another should also be stated; so should responsibility for the provision and maintenance of facilities such as:
Access roads,
Scaffolding,
Cranes and hoists,
Welfare,
Security arrangements,
Storage,
Power supplies,
Water,
Compressed air, and
Telephone