Should the Contractor include the cost of the bond within his tendered total of the Prices?
For ECC contracts using main Options A or B, the Contractor should include the cost of this bond within his tendered total of the Prices. If the Employer wishes the Contractor to price the bond separately in his tender, an appropriate item should be included in the activity schedule or the bill of quantities. For all other Option, the cost of the bond to the Contractor is included within his Fee.