On termination, can the Employer instruct the Contractor to leave the site?
1 Like
Only if P2 applies to the termination (i.e. the Employer has terminated for reasons R1-21 (see Clause 90.2)) can the Employer instruct the Contractor to leave the Site (see Clause 92.2).