The Employer has terminated for a reason which is not listed in the contract in section 91 (R1-21). What is the termination procedure?
1 Like
The Parties follow the procedures outlined in P1 and P2 (Clause 92.1). I.e. the Employer may finish the works and can use any Plant and Materials which he has title to and the Employer may instruct the Contractor to leave the Site and removing any Equipment, Plant and Materials from the Site and hand over any work which he has subcontracted, to the Employer.