A Contractor, working on a maintenance scheme, has damaged existing infrastructure, which was not part of the works. Is the repair to the damaged infrastructure disallowed cost?
1 Like
I would have thought this would come under the third insurance in the table in Clause 84.2, which is to be provided by the Contractor.