ECC Option D: Contractor incurred cost related to repeated testing of plant & materials.
Does the cost of repeated testing disallowed?
As a generalisation ‘No’, although there are two possible headings of Disallowed Cost which MIGHT come into play :
-
has the Contractor not followed a related acceptance of procurement procedure stated in the Works Information, which has resulted in the need for repeating the testing ? If not, then it could be a Disallowed Cost under the 3rd main, 1st sub-bullet of clause 11.2 (25).
-
is the Contractor correcting a Defect caused by him not complying with a constraint for how he is to Provide the Works stated in the Works Information ? If not, then it could be a Disallowed Cost under the 5th main bullet of clause 11.2 (25).
Worth also pointing out here in addition to Jon’s comments that clause 40.6 that states that any Employer cost incurred in having to repeat a test or inspection following a defect is recoverable from the Contractor.