I am trying to understand how the Contractor can change terminal float when CE’s are raised and which accepted programme they should use when costing CE’s. The duration’s are for discussion only but in summary.
1 - A programme is submitted to and accepted by the PM (Rev A) which shows 10 days terminal float
2 - A CE2 is then issued by the PM which will delay the contract by 3 days.
3 - An earlier CE (say CE1) is submitted to the PM by the contractor with a revised programme (Rev B) that moves the Planned Completion and reduces the terminal float by 3 days. This CE and programme are accepted
4 - The contractor then submits CE2 with a new programme (Rev C) and the terminal float is back to 10 days. This programme also moves the contractual date out by 3 days.
When asked, the Contractor have said that they based CE2 on the programme accepted at the time the CE was raised, IE Rev A, and not any subsequently accepted programmes. The reduction in Terminal Float on Rev B was because CE2 hadn’t been accepted and they couldn’t change the Contractual Date.
So, which programme should the Contractor use when looking at the CE? The one accepted at the time the CE is raised or the one accepted when they actually do their costs?
I understand that Terminal Float is the Contractors’ but the client has (understandably) asked why we are accepting any delay as the Contractor is due to finish 4 weeks ahead of planned Completion anyway even with these delays. As a result, I need to either provide the client with an explanation why the earlier programme is the correct one to use or suggest to the contractor that they change CE2.