If an item is missing in an Accepted Programme now that PM and Contractor realise there is an error on it. Can PM using clause 32.1 to instruct the Contractor to submit a revised programme?
Absolutely - exactly what that clause is there for. The Contractor then has to submit a revised programme within the period of reply for acceptance correcting the known mistake, otherwise that programme will not be accepted.