Clause 11.2(22) is as follows:
"Defined Cost is the cost of the components in the Shorter Schedule of Cost Components whether work is subcontracted or not . . . . . . . "
Are there any circumstances under which the Project Manager would or should consider accepting a compensation event quotation where the subcontractor element comprises the actual cost paid to a subcontractor rather than Defined Cost of the subcontracted element?