NEC4 ECS – Option A
Project – New spine road within a greenfield site
Hello,
I was wondering if you are able to provide some further information with regards to mitigation within Cl62 impact programmes, in the following two examples:
- Additionally instructed works that are offline.
- Works by others are not complete by the date shown in the accepted Cl32 programme.
Additionally instructed works that are offline.
We have received an instruction (and CE) to carry out works to raise an existing manhole to a new level to tie in with the construction of the new road we are building. These works are offline and have little effect on works around the area of where the road ties in. The subcontractor has produced a Cl62 programme inserting these works within the accepted Cl32 (maintaining exactly the same logic as was previously shown in the Cl32 albeit these works are now included) and showing no mitigation of how other works can still proceed unaffecting this and mitigating the overall impact to planned completion. Is this correct or should they be showing mitigation to calculate the realistic impacts of the event rather than carrying the exact same logic as the accepted Cl32?
Works by others are not complete by the date shown in the accepted Cl32 programme.
Others (installation of site utilities) under the contract are not finished by the date shown. The logic in the accepted programme shows a finish start for the commencement of follow on works from completion of the others works. Others have not 100% completed their works but the works that have been completed allow the subcontractor to carry out works. Should the Cl62 programme have mitigation showing the works the subcontractor is unable to do? Or should the Cl 62 programme maintain the exact same logic as the accepted CL32 programme showing no mitigation?
Other points of consideration:
- NEC4 guidance notes – Clause 63.5
- “In assessing the effect, risk allowances and mitigation measures should be included on the basis that the Contractor reacts competently and promptly to the event. The intention is that the logic in the Accepted Programme is used as the basis for determining the effect of the compensation event upon planned Completion subject only to changes required as a direct result of the compensation event assessment. ”
- I think that risk allowances and mitigation measures apply to the whole of the Cl 62 programme produced to assess the impact. The Subcontractors opinion is this is just in relation to the initial prompt reaction to the event.
- “In assessing the effect, risk allowances and mitigation measures should be included on the basis that the Contractor reacts competently and promptly to the event. The intention is that the logic in the Accepted Programme is used as the basis for determining the effect of the compensation event upon planned Completion subject only to changes required as a direct result of the compensation event assessment. ”
- NEC4 ECC practice note – October 2017 - Assessing delays due to compensation events
- “It may be that the assessment of delay using the Accepted Programme identifies an obvious error which does not show a genuine forecast effect of the CE on planned completions. In this situation the Project Manager and Contractor should resolve the problem in the logic of the Accepted Programme. To recap, the objective is to assess the effect due to the CE and not due to other factors”
- Obligation to mitigate under law.
- I know that under law you have an obligation to minimise loss and to avoid taking unreasonable steps that increase its loss.
- I am not sure if this is applicable in any way.
- I know that under law you have an obligation to minimise loss and to avoid taking unreasonable steps that increase its loss.