Is a change to the Works Information in order to resolve an ambiguity, a compensation event?

Is a change to the Works Information in order to resolve an ambiguity or inconsistency a compensation event?

1 Like

Yes. This is a compensation event under Clause 60.1(1). The ‘contra proferentum’ rule in Clause 63.8 is used to assess this event.