If a compensation event arises from ambiguities or inconsistencies in the Works Information, how is the event assessed?
The event is assessed as if the Prices, the Completion Date, and the Key Dates were for the interpretation most favourable to the Party which did not draft the Works Information (see Clause 63.8).