How is the Defined Cost for compensation events assessed?
The Defined Cost for compensation events is assessed using the:
Defined Cost current at the time of assessing the compensation event adjusted to base date by dividing by one plus the Price Adjustment Factor for the last assessment of the amount due and
Defined cost at base date levels for amounts calculated from rates stated in the Contract Data for employees and Equipment (see Clause X1.3).