When assessing compensation event for prolongation cost, should the cost of financial issue be taken into account, such as loss of interest for delay in release of retention money and/or financial charges by bank etc?
2 Likes
The items you mentioned are not Defined Costs, so the answer is ‘No’.
2 Likes
Thanks again for your prompt reply
1 Like