How is a compensation event handled if, when the Contractor submits quotations for a compensation event, he has not submitted a programme or alterations to a programme which the contract requires him to submit?

How is a compensation event handled if, when the Contractor submits quotations for a compensation event, he has not submitted a programme or alterations to a programme which the contract requires him to submit?

The Project Manager will assess the compensation event (see Clause 64.1).