How is a compensation event assessed if the Contractor has not submitted a programme or alterations to a programme for acceptance as required by the contract?

How is a compensation event assessed if the Contractor has not submitted a programme or alterations to a programme for acceptance as required by the contract?

The Project Manager assesses the event using his own assessment for the remaining work (see Clause 64.2).