How is a compensation event handled if the Contractor has not submitted a quotation and details of his assessment within the time allowed?

How is a compensation event handled if the Contractor has not submitted a quotation and details of his assessment within the time allowed?

The Project Manager will assess the compensation event (see Clause 64.1).