What 4 tests does the Project Manager apply to a compensation event notified by the Contractor in order to decide whether or not to instruct the Contractor to submit quotations for its effect?

What 4 tests does the Project Manager apply to a compensation event notified by the Contractor in order to decide whether or not to instruct the Contractor to submit quotations for its effect?

1 Like

The event: has arisen from a fault of the Contractor; has not happened and is not expected to happen; Has no effect on Defined Cost, Completion or meeting a Key Date; Is not one of the compensation events stated in this contract (see Clause 61.4).