Does the Project Manager’s or the Supervisor’s acceptance of the Contractor’s communication or of his work change the Contractor’s responsibility to Provide the Works or his liability for his design?
1 Like
No. As stated in Clause 14.1, the Project Manager’s or the Supervisor’s acceptance of the Contractor’s work or a communication from the Contractor, does not alter the Contractor’s responsibility to Provide the Works or his liability for his design.