Does the Project Manager’s or the Supervisor’s acceptance of the Contractor’s communication or of his work change the Contractor’s responsibility to Provide the Works or his liability for his design?

Does the Project Manager’s or the Supervisor’s acceptance of the Contractor’s communication or of his work change the Contractor’s responsibility to Provide the Works or his liability for his design?

1 Like

No. As stated in Clause 14.1, the Project Manager’s or the Supervisor’s acceptance of the Contractor’s work or a communication from the Contractor, does not alter the Contractor’s responsibility to Provide the Works or his liability for his design.