Why might the Project Manager not accept the Contractor’s programme?
Clause 31.3 lists the four reasons why the Project Manager can reject a programme or revised programme. If the programme does not: show information which the contract requires; realistically represent the Contractor’s plans; comply with the Works Information the Project Manager can reject it. He can also reject the programme if it shows plans which are not workable. If the Project Manager does not accept the programme for reasons other than those listed in Clause 31.3, is a compensation event under Clause 60.1(9).